As a Project
Manager, you have to understand Leads and Lags concepts to make Project
Schedule diagram and also necessary to keep track of activity duration.
Lets understand
that:
Leads:
Generally,
Second activity starts when first activity finish, but some time the scenario
is different like two activities can be processed parallely. For example,
second acitivity can be started after few days of first activity finished. If
you want to start editing photographs of Photo session of 4 days schedule then
its not necessary to wait till 4 days to finish full session and then start
editing, on the other hand photo editing can be started after 1 day of photo
session and both activities can be proceed in parallely way.
Lets say
activity A duration is 5 days and activity B duration is 3 days. Activity B can
be started after 3 days of Activity A is started then 2 days are called Lead
here. Its called Finish to Start with 2 days lead, means Activity b can be
started after 3 days of activity A finished. Lead can be used only in Finish to
start activity relationship.
Lags:
Lag is when
successor activity is delayed that much amount of time due to predecessor
activity. Lets say Activity B can be started after 3 days of Activity A
finished then 3 days are called Lag in this scenario.
Lets say, after
photo shoot session, printing of photo will have to start but before that photo
will be sent to customer for proof. So after 10 days of lag we can start the
photo printing when we get customer approval.
No comments:
Post a Comment